We are approaching the final stretch of our works on the San Sebastián metro: a new 2.2 km section, constructed almost entirely in tunnel.
The works were visited this week by the Basque Government’s Minister for Sustainable Mobility of the Basque Government, Susana García Chueca, accompanied by Deputy Minister Miguel Ángel Páez, ETS´s CEO, Antonio López, and Euskotren´s CEO, Javier Seoane.
Accompanied by Azvi’s Regional Director for Civil Works North , José Antonio Varela, as well as other representatives of the joint venture carrying out the works (COMSA, Nortúnel and Campezo), the delegation were able to see the advanced stage of the works:
🔹Altza-Galtzaraborda section: slab track installation(1,940 m) completed, with only a short section of approximately 140 m of ballast track remaining in the area closest to Galtzaraborda.
🔹Pasajes Station: final finishing works are nearing completion.
🔹Galtzaraborda area: works continue to complete the track and connect the station with the current track.
🔹Gure Zumardia Square: urban works on the segment between Hamarretxeta and Gelasio Aramburu are complete, with works continuing on the remainder of the square.
We continue making progress on a key infrastructure project to promote more sustainable, efficient, and connected mobility in San Sebastián and its metropolitan area, encouraging the use of rail public transport as the alternative for the future.