Azvi starts final works of turnout renewal on the Madrid-Seville HSR line
These works represent a major technical and logistical challenge, as they involve the installation of 51 state-of-the-art AV4 points, measuring up to 175 metres and weighing 170 tonnes. They also require the participation of more than 100 specialists, while maintaining daytime traffic on the line.