The President of Adif previews the new Chamartín-Clara Campoamor station concourse

The president of ADIF, María Luisa Domínguez, yesterday previewed the new concourse that will serve the Madrid Chamartín-Clara Campoamor station. 

She was accompanied by Azvi’s CEO, Roberto Gallardo Fernández-Díez, the manager of the Chamartín Vías-Azvi joint venture, José Montero, our Railway area director, César Domínguez González-Seco, Grupo Azvi’s director of IR, Communication and CR, Elena Crespo, and members of the works team, together with other executives from the railway administrator. 

In a joint venture with Vías y Construcciones S.A., we have carried out the restoration of the former 1970s vestibule, abandoned for over 30 years, Aafter commissioning, the station will provide a direct connection between the Suburban,High speed and Metro networks, giving users faster access and  more agile transfers. 

Our work has included: 

  • The demolition of raised flooring, false ceilings, installations and other existing elements, as well as part of the canopies on platforms 1, 2, 3, 4, 5 and 7.
  • Construction of new pillars in the area of the vestibule.
  • Reconfiguration of the space and execution of new finishes.
  • Construction of new mezzanine floor slab.
  • Interior refurbishment of the existing lobby.
  • Refurbishment of the entrances, escalators and stairways, connecting with platforms.
  • Work and installation of new lifts connecting to platforms. 

We are now continuing work on the renovation of platforms and tracks at the station. 

 

Photos: Azvi

Explorar