Azvi continues to make progress on the construction of the San Sebastián metro bypass
At Pasaia station, we are completing the construction of the screens, carrying out the excavation using a hydro-cutter. In the tunnel, the excavation and support of the 334-metre-long evacuation and ventilation gallery has been completed. In total, more than 800 metres of the 830 metres